Renovations Continue

Oh Oh! After the cabinet guys left I discovered that shelves in the new cabinets (not the refaced ones) were unstable. My observation … they are too narrow but I am not a cabinet maker.

counters 005 copy

Even so they need to be stabilized so they don’t fall down all the time. I called the 800 customer care line and explained my problem. They said they would let the project manager know and have him call me. That was yesterday morning.

7 am my phone rang. The counter folks were early! They were out front and ready to start the installation. I told them give me 5 minutes to get dressed and I’ll let you in. By 9 am the big pieces were in. It took another 2 hours for the back splashes, holes for the facet etc on the sink and the caulk. I don’t know how anyone else will feel about the counters but I absolutely love them!

counters 001 copy

Such an improvement over the old white counters. The greens in the pattern match the soft green of the cabinets perfectly too. You never know if that tiny sample will really look as good in real life as it did in your imagination.

counters 002 copy

Everything has to set and dry so the plumber won’t be out until Monday. 🙁

counters 006 copy

About 9:30 the phone rang again. It was the project manager. I explained the problem with the shelves to him and he said he’d send the cabinet guys back…if not today he’d send them Saturday. I told him I could wait til Monday because I needed to go shopping Saturday for new shelf liners and a few other things to organize the cabinets. I want to start putting stuff away.

counters 004 copy

I scheduled the tile install with him for Wednesday and Friday. I guess they do all the tile first then come back the next day to caulk. Since Thursday is Thanksgiving we’re going to do Wednesday and Friday. The kitchen will be functional to cook even if its not 100% done.

This is dragging out longer than they told me but it’s partly my fault. I couldn’t go Monday – Friday because of work commitments on Thursday. That made the job spill over to Monday.

The tile people could have come Monday but I want to add another outlet near the stove so my electrician needs to get here  to put in the box for the outlet before they tile. I need to give him time to come in first.  I am scheduled to work in the Foxboro office on Tuesday so can’t have anyone here then so Wednesday was the only logical choice. But we are making progress!

 

 

 